Skip to content
Decision madeHarbour facilities· TR030006

Able Marine Energy Park Material Change 2

A nationally significant infrastructure project in East Riding, North Lincs. A decision has been made. We are confirming the outcome.

Free. We'll email you when it moves stage: consultation, submission, examination and decision.

Where it is in the process

  1. Pre-application
  2. Submitted
  3. Pre-examination
  4. Examination
  5. Recommendation
  6. Decision due
  7. Decision made

The site

The outline is the boundary the promoter published. It can include cable, pipeline or road routes as well as the main site. 647 hectares inside the published boundary.

What is proposed

Two amendments to the layout of the quay that was authorised by the Able Marine Energy Park Development Consent Order 2014 and one amendment to a footpath diversion to go round the end of a railway rather than crossing it.

Contains public sector information licensed under the Open Government Licence v3.0. © Crown copyright and database right 2026.