Eggborough Power Station Selby Road Eggborough East Yorkshire
Approved on 12 March 2026
Council decision: Condition decisionDelegated (officer decision)
Proposal
Discharge of condition 30 (surface water) of approval ZG2025/0392/S73 Section 73 application to vary conditions 03 (plans) and 04 (appearance, scale & layout) of approval ZG2024/0737/S73 Section 73 application to vary condition 15 (30 year Biodiversity Enhancement Management and Monitoring Plan), and delete conditions 16 (Ecological Enhancement Measures) and 26 (surface water) of approval 2022/1105/FULM Construction and operation of a battery energy storage system with an electrical output capacity of up to 500MW and associated development including substation, control building(s), electrical cabling including below ground 400kV cabling, roadways and modified accesses, site security infrastructure, lighting, boundary treatments and landscaping granted on 17 January 2023
- Received
- 16 January 2026
- Decision level
- Delegated (officer decision)
- Public comments
- 2
- Council
- Selby
- Ward
- Osgoldcross
- Agent
- DWD Property and Planning
- ReceivedReceived16 Jan
- ValidatedValidated16 Jan
- Consult.Consultation13 Feb
- TargetTarget Date13 Mar
- DecidedDecided12 Mar
Decided in 55 days (council typically 56)
About this application
This is an application to vary a condition at Eggborough Power Station Selby Road Eggborough East Yorkshire. Selby has handled 519 applications of this type. This one was decided in 55 days. There have been 25 other applications at this address. In the past year there have been 42 applications across Osgoldcross.
95% of conditions applications at Selby were approved. Across all application types, the council typically decides in about 8 weeks (median).
Based on decided applications received in the last 3 years.Planning something similar? See what gets approved on your street
Application details
- Application type
- Discharge of Planning Condition
- Scale / size
- Small
- Parish
- Eggborough Parish Council
Planning application dates
- Date validated
- 16 January 2026
- Consultation expiry
- 13 February 2026
- Consultation start
- 23 January 2026
- Consultation end
- 13 February 2026
- Last date for comments
- 1 February 2026
- Target decision date
- 13 March 2026
Applicant and agent
- Agent
- DWD Property and Planning
- Agent address
- DWD Property And Planning 69 Carter Lane LONDON EC4V 5EQ
Planning decision
- Statutory period
- 56 days
Additional information
- Planning Portal ID
- PP-14628332
- Documents
- 8
- Constraints
- 132
Site constraints
Designations at the address point. Ones next to the site may also apply.
- Flood zone 1: Low probability (rivers and sea)
Not published by this council, so not checked: Article 4 directions and tree preservation orders. Ask the council if these matter.
Also checked, none recorded (22)
flood storage areas, conservation areas, listed buildings, green belt, scheduled monuments, World Heritage Sites, World Heritage Site buffer zones, registered parks and gardens, registered battlefields, Heritage at Risk entries, nutrient neutrality catchments, national parks, National Landscapes, SSSIs, Special Areas of Conservation, Special Protection Areas, Ramsar sites, ancient woodland, national nature reserves, local nature reserves, heritage coasts and brownfield registers.
A guide only, from official open data; it is not a planning search. Flood zones cover rivers and sea, not surface water.
Data © Crown copyright and others · sources and licences
Contains public sector information from planning.data.gov.uk (MHCLG and local planning authorities), licensed under the Open Government Licence v3.0. © Crown copyright and database right 2026.
© Historic England 2026. Contains Ordnance Survey data © Crown copyright and database right 2026. The Historic England GIS Data contained in this material was obtained on 2026-11-03. The most publicly available up to date Historic England GIS Data can be obtained from HistoricEngland.org.uk.
© Natural England copyright. Contains Ordnance Survey data © Crown copyright and database right 2026.
© Environment Agency copyright and/or database right 2026. All rights reserved. Flood Map for Planning, Open Government Licence v3.0.
Contains Ordnance Survey data © Crown copyright and database right 2026.
Source: Office for National Statistics licensed under the Open Government Licence v.3.0. Contains OS data © Crown copyright and database right 2026.
Planning history at this site
20 other applications at this property, newest first.
- 202530 Sep
Discharge of condition 19 (foul & surface water drainage) in relation to Plots 3/4A-D of approval…
Condition decisionDischarge of conditionsZG2025/0991/DOC - 202529 Aug
Reserved Matters application for the construction of employment development (Use Class E(g)iii, B2 and B8)…
ApprovedReserved mattersZG2025/0884/REMM - 202427 Mar
Discharge of requirement 17 (Protected Species) 'The Eggborough Gas Fired Generating Station Order 2018'…
Condition decisionDischarge of conditionsZG2024/0301/DOC - 202314 Nov
Discharge of requirement 25 (Piling and Penetrative Foundation Design) of the 'The Eggborough Gas Fired…
Condition decisionDischarge of conditionsZG2023/1214/DOC - 202314 Nov
Discharge of requirement 5 (detailed design) of the 'The Eggborough Gas Fired Generating Station Order 2018'…
WithdrawnDischarge of conditionsZG2023/1213/DOC - 20236 Nov
Discharge of requirement 18 Construction Environmental Management Plan 2017/0070/GOV
Condition decisionDischarge of conditionsZG2023/1184/DOC - 20233 Nov
Discharge of requirement 6 (landscaping and biodiversity protection, management and enhancement plan) of the…
Condition decisionDischarge of conditionsZG2023/1183/DOC - 20231 Nov
Discharge of requirement 34 (Employment, skills and training plan) of the 'The Eggborough Gas Fired…
Condition decisionDischarge of conditionsZG2023/1169/DOC - 20231 Nov
Discharge of requirement 29 (Aviation Warning Lighting) of the 'The Eggborough Gas Fired Generating Station…
Condition decisionDischarge of conditionsZG2023/1171/DOC - 20231 Nov
Discharge of requirement 30 (Air Safety) of the 'The Eggborough Gas Fired Generating Station Order 2018'…
Condition decisionDischarge of conditionsZG2023/1170/DOC - 202331 Oct
Partial discharge of requirement 13 (Surface & foul water drainage) of the 'The Eggborough Gas Fired…
Conditions part dischargedDischarge of conditionsZG2023/1162/DOC - 202331 Oct
Partial discharge of requirement 14 (Flood Risk Mitigation) of the 'The Eggborough Gas Fired Generating…
Condition decisionDischarge of conditionsZG2023/1163/DOC - 202330 Oct
Partial discharge of requirement 17 (protected species) of the 'The Eggborough Gas Fired Generating Station…
Condition decisionDischarge of conditionsZG2023/1158/DOC - 202323 Oct
Partial discharge of requirement 9 (Highway accesses) of the 'The Eggborough Gas Fired Generating Station…
Condition decisionDischarge of conditionsZG2023/1118/DOC - 202323 Oct
Partial discharge of requirement 16 (Archaeology) of the 'The Eggborough Gas Fired Generating Station Order…
Conditions part dischargedDischarge of conditionsZG2023/1120/DOC - 202323 Oct
Partial discharge of requirement 7 (Public rights of way diversions) of the 'The Eggborough Gas Fired…
Condition decisionDischarge of conditionsZG2023/1117/DOC - 202323 Oct
Partial discharge of requirement 10 (Means of enclosure) of the 'The Eggborough Gas Fired Generating Station…
Condition decisionDischarge of conditionsZG2023/1119/DOC - 202311 Sep
Discharge of requirement 21 (construction worker travel plan) of the 'The Eggborough Gas Fired Generating…
Condition decisionDischarge of conditionsZG2023/0965/DOC - 202311 Sep
Discharge of requirement 23 (noise and vibration monitoring) of the 'The Eggborough Gas Fired Generating…
Condition decisionDischarge of conditionsZG2023/0964/DOC - 202311 Sep
Discharge of requirement 26 (Waste management on site - construction wastes) of the 'The Eggborough Gas Fired…
Condition decisionDischarge of conditionsZG2023/0967/DOC
Source: Selby
Track this application
Get email alerts when there is a planning decision or status change.
Around this site
Nearby applications
- Eggborough Power Station Wand Lane Hensall East YorkshireZG2026/0474/TELC · TelecomsAwaiting decision0.1 mi
- Air Gas Production Limited Eggborough Power Station Wand Lane Hensall Goole North Yorkshire DN14 0BS26/04138/FUL · FullApproved0.2 mi
- Eggborough Power Station Selby Road Eggborough East YorkshireZG2025/0884/REMM · OutlineApproved0.2 mi
- Eggborough Power Station Selby Road Eggborough East YorkshireZG2025/0991/DOC · ConditionsApproved0.3 mi
- Pumping Station Wand Lane Hensall East YorkshireZG2025/0052/FULM · FullAwaiting decision0.4 mi
For applicants and trades
Contractors near this project
- Channel Healthcare Ltd1.2 mi
- A P Brown ElectricalElectrician1.4 mi
- MDS Electrical ContractorsElectrician1.7 mi
- Ladbroke Court LtdElectrician1.7 mi
Planning something similar?
See what the council approved and refused on your street for the project you have in mind. Pick your home and get the evidence before you pay for drawings.