Eggborough Power Station Selby Road Eggborough East Yorkshire
Approved on 12 January 2024
Council decision: Condition decisionDelegated (officer decision)
Boundary © HM Land Registry, © Ordnance Survey · details
This information is subject to Crown copyright and database rights 2026 and is reproduced with the permission of HM Land Registry. The polygons (including the associated geometry, namely x, y co-ordinates) are subject to Crown copyright and database rights 2026 Ordnance Survey AC0000851063. Conditions of use.
Proposal
Partial discharge of requirement 17 (protected species) of the 'The Eggborough Gas Fired Generating Station Order 2018' ('the Order') relates to - 2017/0070/GOV
- Received
- 30 October 2023
- Decision level
- Delegated (officer decision)
- Public comments
- 1
- Council
- Selby
- Ward
- Osgoldcross
- ReceivedReceived30 Oct
- ValidatedValidated31 Oct
- Consult.Consultation27 Nov
- TargetTarget Date26 Dec
- DecidedDecided12 Jan
Decided in 73 days (council typically 56)
About this application
This is an application to discharge conditions at Eggborough Power Station Selby Road Eggborough East Yorkshire. Selby has handled 519 applications of this type. This one was decided in 74 days, 3 weeks longer than Selby's typical decision time. There have been 25 other applications at this address. In the past year there have been 42 applications across Osgoldcross.
95% of conditions applications at Selby were approved. Across all application types, the council typically decides in about 8 weeks (median).
Based on decided applications received in the last 3 years.Planning something similar? See what gets approved on your street
Application details
- Application type
- Discharge of Planning Condition
- Scale / size
- Small
- Parish
- Eggborough Parish Council
Planning application dates
- Date validated
- 31 October 2023
- Consultation expiry
- 27 November 2023
- Consultation start
- 6 November 2023
- Consultation end
- 27 November 2023
- Last date for comments
- 27 November 2023
- Target decision date
- 26 December 2023
Planning decision
- Statutory period
- 56 days
Additional information
- Documents
- 7
- Constraints
- 218
Site constraints
Designations that overlap or adjoin the site outline.
- Flood zone 3: High probability (rivers and sea)
Not published by this council, so not checked: Article 4 directions and tree preservation orders. Ask the council if these matter.
Also checked, none recorded (22)
flood storage areas, conservation areas, listed buildings, green belt, scheduled monuments, World Heritage Sites, World Heritage Site buffer zones, registered parks and gardens, registered battlefields, Heritage at Risk entries, nutrient neutrality catchments, national parks, National Landscapes, SSSIs, Special Areas of Conservation, Special Protection Areas, Ramsar sites, ancient woodland, national nature reserves, local nature reserves, heritage coasts and brownfield registers.
A guide only, from official open data; it is not a planning search. Flood zones cover rivers and sea, not surface water.
Data © Crown copyright and others · sources and licences
Contains public sector information from planning.data.gov.uk (MHCLG and local planning authorities), licensed under the Open Government Licence v3.0. © Crown copyright and database right 2026.
© Historic England 2026. Contains Ordnance Survey data © Crown copyright and database right 2026. The Historic England GIS Data contained in this material was obtained on 2026-11-03. The most publicly available up to date Historic England GIS Data can be obtained from HistoricEngland.org.uk.
© Natural England copyright. Contains Ordnance Survey data © Crown copyright and database right 2026.
© Environment Agency copyright and/or database right 2026. All rights reserved. Flood Map for Planning, Open Government Licence v3.0.
Contains Ordnance Survey data © Crown copyright and database right 2026.
Source: Office for National Statistics licensed under the Open Government Licence v.3.0. Contains OS data © Crown copyright and database right 2026.
Associated applications
- 202330 Oct
Partial discharge of requirement 17 (protected species) of the 'The Eggborough Gas Fired Generating Station…
This applicationCondition decisionDischarge of conditionsZG2023/1158/DOC - 202323 Oct
Partial discharge of requirement 7 (Public rights of way diversions) of the 'The Eggborough Gas Fired…
Condition decisionDischarge of conditionsZG2023/1117/DOC - 202323 Oct
Partial discharge of requirement 9 (Highway accesses) of the 'The Eggborough Gas Fired Generating Station…
Condition decisionDischarge of conditionsZG2023/1118/DOC - 202323 Oct
Partial discharge of requirement 10 (Means of enclosure) of the 'The Eggborough Gas Fired Generating Station…
Condition decisionDischarge of conditionsZG2023/1119/DOC - 202323 Oct
Partial discharge of requirement 16 (Archaeology) of the 'The Eggborough Gas Fired Generating Station Order…
Conditions part dischargedDischarge of conditionsZG2023/1120/DOC - 202311 Sep
Discharge of requirement 12 (fire prevention) of the 'The Eggborough Gas Fired Generating Station Order 2018'…
Condition decisionDischarge of conditionsZG2023/0962/DOC - 202311 Sep
Discharge of requirement 20 (Construction traffic management plan) of the 'The Eggborough Gas Fired…
WithdrawnDischarge of conditionsZG2023/0963/DOC - 202311 Sep
Discharge of requirement 23 (noise and vibration monitoring) of the 'The Eggborough Gas Fired Generating…
Condition decisionDischarge of conditionsZG2023/0964/DOC - 202311 Sep
Discharge of requirement 21 (construction worker travel plan) of the 'The Eggborough Gas Fired Generating…
Condition decisionDischarge of conditionsZG2023/0965/DOC - 202311 Sep
Discharge of requirement 26 (Waste management on site - construction wastes) of the 'The Eggborough Gas Fired…
Condition decisionDischarge of conditionsZG2023/0967/DOC - 202325 Jul
Discharge of requirement 8(1) (external lighting) of the 'The Eggborough Gas Fired Generating Station Order…
Condition decisionDischarge of conditionsZG2023/0761/DOC - 202325 Jul
Discharge of requirement 15 (contaminated land and groundwater) of the 'The Eggborough Gas Fired Generating…
PendingDischarge of conditionsZG2023/0763/DOC - 202325 Jul
Discharge of requirement 19 (protection of highway surfaces) of the 'The Eggborough Gas Fired Generating…
Condition decisionDischarge of conditionsZG2023/0764/DOC - 20238 Feb
Discharge of requirement 2 (Commencement of authorised development), and discharge of requirements 5(4)…
Condition decisionDischarge of conditions2023/0151/DOC - 201712 Jan
Application for Development Consent Order (DCO) under the Planning Act 2008 for construction and operation of…
ApprovedDealt with by other government departsPart of2017/0070/GOV
Planning history at this site
13 other applications at this property, newest first.
- 202616 Jan
Discharge of condition 30 (surface water) of approval ZG2025/0392/S73
Condition decisionDischarge of conditionsZG2026/0040/DOC - 202530 Sep
Discharge of condition 19 (foul & surface water drainage) in relation to Plots 3/4A-D of approval…
Condition decisionDischarge of conditionsZG2025/0991/DOC - 202529 Aug
Reserved Matters application for the construction of employment development (Use Class E(g)iii, B2 and B8)…
ApprovedReserved mattersZG2025/0884/REMM - 202427 Mar
Discharge of requirement 17 (Protected Species) 'The Eggborough Gas Fired Generating Station Order 2018'…
Condition decisionDischarge of conditionsZG2024/0301/DOC - 202314 Nov
Discharge of requirement 25 (Piling and Penetrative Foundation Design) of the 'The Eggborough Gas Fired…
Condition decisionDischarge of conditionsZG2023/1214/DOC - 202314 Nov
Discharge of requirement 5 (detailed design) of the 'The Eggborough Gas Fired Generating Station Order 2018'…
WithdrawnDischarge of conditionsZG2023/1213/DOC - 20236 Nov
Discharge of requirement 18 Construction Environmental Management Plan 2017/0070/GOV
Condition decisionDischarge of conditionsZG2023/1184/DOC - 20233 Nov
Discharge of requirement 6 (landscaping and biodiversity protection, management and enhancement plan) of the…
Condition decisionDischarge of conditionsZG2023/1183/DOC - 20231 Nov
Discharge of requirement 34 (Employment, skills and training plan) of the 'The Eggborough Gas Fired…
Condition decisionDischarge of conditionsZG2023/1169/DOC - 20231 Nov
Discharge of requirement 29 (Aviation Warning Lighting) of the 'The Eggborough Gas Fired Generating Station…
Condition decisionDischarge of conditionsZG2023/1171/DOC - 20231 Nov
Discharge of requirement 30 (Air Safety) of the 'The Eggborough Gas Fired Generating Station Order 2018'…
Condition decisionDischarge of conditionsZG2023/1170/DOC - 202331 Oct
Partial discharge of requirement 13 (Surface & foul water drainage) of the 'The Eggborough Gas Fired…
Conditions part dischargedDischarge of conditionsZG2023/1162/DOC - 202331 Oct
Partial discharge of requirement 14 (Flood Risk Mitigation) of the 'The Eggborough Gas Fired Generating…
Condition decisionDischarge of conditionsZG2023/1163/DOC
Source: Selby
Track this application
Get email alerts when there is a planning decision or status change.
Around this site
Nearby applications
- Eggborough Power Station Selby Road Eggborough Goole East Yorkshire2023/0151/DOC · ConditionsApproved0.0 mi
- Eggborough Power Station Selby Road Eggborough East YorkshireZG2023/0963/DOC · ConditionsWithdrawn0.0 mi
- Eggborough Power Station Selby Road Eggborough East YorkshireZG2023/1117/DOC · ConditionsApproved0.0 mi
- Eggborough Power Station Selby Road Eggborough East YorkshireZG2023/0967/DOC · ConditionsApproved0.0 mi
- Eggborough Power Station Selby Road Eggborough East YorkshireZG2023/1184/DOC · ConditionsApproved0.0 mi
For applicants and trades
Contractors near this project
- Channel Healthcare Ltd0.2 mi
- Ladbroke Court LtdElectrician1.2 mi
- GRH Garforth Electrical LtdElectrician1.8 mi
- Busy Energy LtdAir Source Heat Pump2.0 mi
Planning something similar?
See what the council approved and refused on your street for the project you have in mind. Pick your home and get the evidence before you pay for drawings.