Skip to content

RWE npower, Aberthaw Power Station

2012/00239/SC1EIA Screening OpinionPermitted
Outline / PiP

Proposal

Enhanced Biomass project

Received
12 March 2012
Decided
28 March 2012 · Environmental Impact Assessment (Screening) - Not Required
Decision level
Delegated (officer decision)
  1. Received12 Mar
  2. Validated12 Mar
  3. Consult.
  4. Target
  5. Decided28 Mar

Decided in 16 days (council typically 63)

9 weeks typical decision time in Glamorgan71% of outline applications approvedSee what's approved near your address

This is an outline application at RWE npower, Aberthaw Power Station. Glamorgan has handled 242 applications of this type and approves 73% of them, typically deciding them in 54 days. This one was decided in 16 days, 5 weeks quicker than Glamorgan's median. There are no previous applications recorded at this address.

Application Details

Reference
2012/00239/SC1
Address
RWE npower, Aberthaw Power Station
Local Authority
Glamorgan
Application Type
EIA Screening Opinion
Scale / Size
Medium
Decision Status
Permitted
Current Status
Application DETERMINED
Parish
St. Athan Community Council

Applicant & Agent

Applicant Address
RWE npower, Trigonos, Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, SN5 6PB.
Agent Address
RWE npower, Trigonos, Windmill Hill Business Park, Whitehill Way, Swindon, Wiltshire, SN5 6PB.

Planning Application Dates

Date Received
12 March 2012
Date Decided
28 March 2012
Date Validated
12 March 2012
Date Submitted
12 March 2012
Application Expires
2 April 2012

Planning Decision

Decision
Environmental Impact Assessment (Screening) - Not Required
Decided By
Delegated
Statutory Period
21 days

Publicity

Appeal

Additional Information

Documents
4
Coordinates
51.387490, -3.401321
Enriching application data
2/3
Council recordsAppealsFlood risk

Source: Glamorgan

Track this application

Get email alerts when there is a planning decision or status change.

What's been approved on your street?

See what the council approved and refused near this address for the project you have in mind, and the rules that apply here.

Get The Signal Report