Park Place 6 North Road Poole BH14 0LY
Refused on 22 October 2025
Delegated (officer decision)10 reasons for refusal
Proposal
Outline application with Some Matters Reserved for a phased development of up to 115 apartments across 2 separate blocks following demolition of the existing building.
- Received
- 2 July 2025
- Decision level
- Delegated (officer decision)
- Ward
- Parkstone
- ReceivedReceived2 Jul
- ValidatedValidated9 Jul
- Consult.Consultation30 Sep
- TargetTarget Date
- DecidedDecided22 Oct
Decided in 105 days (council typically 63)
About this application
This is an outline application for demolition at Park Place 6 North Road Poole BH14 0LY. BCP has handled 792 applications of this type. This one was decided in 112 days, 7 weeks longer than BCP's typical decision time. There are no previous applications recorded at this address. In the past year there have been 159 applications across Parkstone. We hold 1,124 applications in total for the BH14 postcode area.
76% of outline applications at Bournemouth, Christchurch and Poole Council were approved. Across all application types, the council typically decides in about 9 weeks (median).
Based on decided applications received in the last 3 years.Planning something similar? See what gets approved on your street
Why it was refused
- The design of Block B; due to its proposed depth and height; relative to the neighbouring block of flats at no. 23 with a lack of recess at the upper floors, would result in a dominant boxy design solution; failing to respect or enhance the streetscene or be sympathetic to the surrounding residential scale contrary to PP27, PP28 and the NPPF.
- The design and layout of the scheme is substandard, when viewed from North Road the absence of an active frontage to the street, the volume of built form, undercroft parking areas and hardstanding within the site would result in a dominant and unduly prominent development with limited scope of meaningful landscaping to provide softening or screening contrary to PP27, PP28 and the NPPF.
- The proposed design, due to the layout and proposed footprint of the blocks and proximity to each other would result in poor living conditions to future occupants by way of overlooking, overshadowing and being overbearing and oppressive. A number of the proposed dwellings would have poor quality outlook and are likely to have poor quality internal light levels due to the proximity to built form and/or being single aspect north facing dwellings. As such it is considered that the design and layout is substandard contrary to Policy to PP27 of the Poole Local Plan and NPPF.
- The siting of the proposed Block B and the six storeys of balconies to the rear elevation would result in an overbearing and oppressive relationship to the existing residential properties to the rear along North Road which back onto the application site. The additional floors when compared to the extant scheme, result in a closer proximity to the neighbour and an intensification of direct views from the proposed balconies of 23 flats with direct views into the neighbouring sites would result in a harmful impact on the amenity of the existing residents contrary to Policy to PP27 of the Poole Local Plan and NPPF.
- Due to the proposed layout of development; the undercroft parking areas and spaces between the buildings; the development fails to result in a high quality, secure or safe environment contrary to PP27 and Secured By Design guidance.
- No agreement has been entered into to secure a review mechanism to demonstrate that the proposal is unable to provide affordable housing provision or a financial contribution towards affordable housing in accordance with PP11 and the NPPF.
- Due to the lack of evidence the application is unable to demonstrate that the proposed drainage strategy is appropriate; and would not result in floodrisk elsewhere. Furthermore the proposal is not in accordance with para. 182 of the NPPF which requires SuDs to control flow rates and reduce volumes of runoff and provide multifunctional benefits wherever possible. The proposal is therefore contrary to Poole Local Plan policy PP38 and the NPPF.
- The applicant has failed to provide sufficient justification of the layout/design and how it achieves the BNG hierarchy as per the Town and Country Planning (Development Management Procedure) ( England) Order 2015. Therefore the local planning authority cannot be confident that the statutory biodiversity gain condition can be discharged. Consequently, the local planning authority cannot be confident that the proposed development would comply with the requirements of Schedule 7A of the Town and Country Planning Act 1990 and Schedule 14 of the Environment Act 2021
- The site lies between 400m and 5km of Dorset heathlands which are protected under European legislation for their wildlife importance. The Dorset Heathlands Planning Framework Supplementary Planning Document (SPD) 2020-2025 sets out the means by which the cumulative impacts of additional residential development in this zone can be mitigated. In this instance the proposal fails to secure the mitigation measures identified as necessary in the SPD such that it would be contrary to policy PP32 of the Poole Local Plan and the provisions of the National Planning Policy Framework, particularly paragraph 193.
- The application site is within close proximity to Poole Harbour which is a Special Protection Area (SPA), Site of Special Scientific Interest (SSSI) and Ramsar site and the determination of the application should be undertaken with regard to these European designations and the requirements of the Conservation of Habitats and Species Regulations 2017. The applicant has failed to demonstrate in accordance with the Habitat Regulations that the proposals will cause no harm to the SPA. It is clear, on the basis of advice from Natural England that, notwithstanding the CIL contribution, no avoidance or mitigation of adverse effects through Strategic Access Management and Monitoring (SAMM) has been secured. In the absence of any form of acceptable mitigation it is likely to have an adverse effect on the special features of Poole Harbour including those which are SPA features. Having regard to the Waddenzee judgement (ECJ case C-127/02) the Council is not in a position to be convinced that there is no reasonable scientific doubt to the contrary. For these reasons, and without needing to conclude the appropriate assessment, the proposal is considered contrary to the recommendations of the Berne Convention Standing Committee on urban development adjacent to Poole Harbour, and Policy PP32 and PP39 of the Poole Local Plan (November 2018).
From the council's decision notice.
Application details
- Postcode
- BH14 0LY
- Application type
- Outline Planning Permission
- Scale / size
- Large
- Number of dwellings
- 115
Planning application dates
- Date validated
- 9 July 2025
- Consultation expiry
- 30 September 2025
- Consultation start
- 13 August 2025
- Consultation end
- 30 September 2025
Applicant and agent
- Agent address
- Unit 5 Designer House Sandford Lane Wareham BH20 4DY
Additional information
- Documents
- 103
Site constraints
Designations at the address point. Ones next to the site may also apply.
- Nutrient neutrality catchment: Poole Harbour SPA/RamsarApplies to new homes and overnight accommodation
- Flood zone 1: Low probability (rivers and sea)
Not published by this council, so not checked: Article 4 directions. Ask the council if these matter.
Possibly incomplete for this council: tree preservation orders.
Also checked, none recorded (21)
flood storage areas, conservation areas, listed buildings, green belt, scheduled monuments, World Heritage Sites, World Heritage Site buffer zones, registered parks and gardens, registered battlefields, Heritage at Risk entries, national parks, National Landscapes, SSSIs, Special Areas of Conservation, Special Protection Areas, Ramsar sites, ancient woodland, national nature reserves, local nature reserves, heritage coasts and brownfield registers.
A guide only, from official open data; it is not a planning search. Flood zones cover rivers and sea, not surface water.
Data © Crown copyright and others · sources and licences
Contains public sector information from planning.data.gov.uk (MHCLG and local planning authorities), licensed under the Open Government Licence v3.0. © Crown copyright and database right 2026.
© Historic England 2026. Contains Ordnance Survey data © Crown copyright and database right 2026. The Historic England GIS Data contained in this material was obtained on 2026-11-03. The most publicly available up to date Historic England GIS Data can be obtained from HistoricEngland.org.uk.
© Natural England copyright. Contains Ordnance Survey data © Crown copyright and database right 2026.
© Environment Agency copyright and/or database right 2026. All rights reserved. Flood Map for Planning, Open Government Licence v3.0.
Contains Ordnance Survey data © Crown copyright and database right 2026.
Source: Office for National Statistics licensed under the Open Government Licence v.3.0. Contains OS data © Crown copyright and database right 2026.
Source: BCP
Track this application
Get email alerts when there is a planning decision or status change.
Get email alerts near BH14
New planning applications delivered to your inbox daily.
Around this site
Nearby applications
- 49 North Road Poole BH14 0LTP/26/00172/HOU · FullApproved0.0 mi
- 39 Commercial Road Poole BH14 0HUP/26/00852/TTPO · TreesApproved0.0 mi
- 28 Chapel Road Poole BH14 0JUP/26/00084/HOU · FullApproved0.1 mi
- 63 Church Road Poole BH14 0NSP/26/00728/CONDR · ConditionsRefused0.1 mi
- 1 Old School Close Poole BH14 0NLP/26/02816/TCA · TreesApproved0.1 mi
For applicants and trades
Contractors near this project
Find contractors for demolition near this site- Adelec LtdElectrician0.0 mi
- Clabo LimitedElectrician0.1 mi
- Hancox Electrical Services LtdElectrician0.1 mi
- Marco Home Improvements LimitedWindow & Door Installer0.2 mi
Planning something similar?
See what the council approved and refused for new homes on your street. Pick your home and get the evidence before you pay for drawings.