Sheringham and Dudgeon Extension Projects
A nationally significant infrastructure project in Norfolk, South Norfolk Broadland, North Norfolk. A decision has been made. We are confirming the outcome.
Free. We'll email you when it moves stage: consultation, submission, examination and decision.
Where it is in the process
- Pre-application
- Submitted
- Pre-examination
- Examination
- Recommendation
- Decision due
- Decision made
The site
The outline is the boundary the promoter published. It can include cable, pipeline or road routes as well as the main site. 43,273 hectares inside the published boundary.
What is proposed
Sheringham Extension Project has a maximum installed capacity of 317MW, while Dudgeon Extension Project has a maximum installed capacity of 402MW. Joint export cable system, offshore and onshore, connecting to the national grid transmission network at Norwich Main substation.