Decision madeElectricity lines· EN020021
Reinforcement to North Shropshire Electricity Distribution Network
A nationally significant infrastructure project in Shropshire. A decision has been made. We are confirming the outcome.
Free. We'll email you when it moves stage: consultation, submission, examination and decision.
Where it is in the process
- Pre-application
- Submitted
- Pre-examination
- Examination
- Recommendation
- Decision due
- Decision made
The site
The outline is the boundary the promoter published. It can include cable, pipeline or road routes as well as the main site. 93 hectares inside the published boundary.
What is proposed
The installation of a new 132kV overhead line Trident design i.e comprising 3 conductors supported by mostly single wood poles at a height of between 12m to 14m over span lengths of an average distance of 120m.