Skip to content
Decision madeElectricity lines· EN020014

North Wales Wind Farms Connection

A nationally significant infrastructure project in Conwy, Denbighshire. A decision has been made. We are confirming the outcome.

Free. We'll email you when it moves stage: consultation, submission, examination and decision.

Where it is in the process

  1. Pre-application
  2. Submitted
  3. Pre-examination
  4. Examination
  5. Recommendation
  6. Decision due
  7. Decision made

The site

The outline is the boundary the promoter published. It can include cable, pipeline or road routes as well as the main site. 2,016 hectares inside the published boundary.

What is proposed

Construction of 132kV circuit between TAN Area A and SP Manweb's St Asaph grid substation.