Planning applications in EC2N
We hold 144 planning applications for the EC2N postcode area, 48 of them submitted in the past year. 100% of decided applications here were approved. A decision typically takes 60 days. The area is covered by City of London, Tower Hamlets, Greenwich.
Councils covering EC2N
Recent applications in EC2N
Submission of details pursuant to discharge of condition 2(a) of planning permission 24/01203/FULL dated 02.06.2025.
Submission of details pursuant to discharge of condition 2(a) of planning permission 24/01203/FULL dated 02.06.2025.
Submission of masonry report and drawings pursuant to discharge of condtion 3(b), 5 & 6 of planning permission 24/00812/LBC dated 04.12.2024.
Submission of masonry report and drawings pursuant to discharge of condtion 3(b), 5 & 6 of planning permission 24/00812/LBC dated 04.12.2024.
Submission of the Local Procurement Strategy (Demolition and Construction) pursuant to Schedule 3, Paragraph 2.1.1 of the S106 Agreement dated 7th November 2025 (Planning Application Reference: 25/00540/FULL).
Submission of the Local Procurement Strategy (Demolition and Construction) pursuant to Schedule 3, Paragraph 2.1.1 of the S106 Agreement dated 7th November 2025 (Planning Application Reference: 25/00540/FULL).
Submission of Prediction of Operational Energy Consumption Report pursuant to discharge of condition 8 of planning permission 25/00041/FULMAJ dated 19.02.2026.
Submission of Prediction of Operational Energy Consumption Report pursuant to discharge of condition 25/00041/FULMAJ dated 19.02.2026.
Submission of details of (i) section and elevation of agreed typical bays, including agreed typical bays (ii) details of walls, railings, balustrades etc, (iii) details of the integration of window cleaning equipment (iv) Details of access to the roof for cleaning and maintenance (v) Details of the cycle stand types and setting out of long stay cycle spaces (vi) Details of sanitary facilities including accessible toilets pursuant to conditions 2 (b), (c), (d), (g) and (h) and 3 (c) and (d) of Planning Permission 25/00540/FULL dated 07.11.2025.
Submission of details of (i) section and elevation of agreed typical bays, including agreed typical bays (ii) details of walls, railings, balustrades etc, (iii) details of the integration of window cleaning equipment (iv) Details of access to the roof for cleaning and maintenance (v) Details of the cycle stand types and setting out of long stay cycle spaces (vi) Details of sanitary facilities including accessible toilets pursuant to conditions 2 (b), (c), (d), (g) and (h) and 3 (c) and (d) of Planning Permission 25/00540/FULL dated 07.11.2025.
Application for a non-material amendment under Section 96A of the Town and Country Planning Act 1990 (as amended) to planning permission reference 4931B (dated 16 April 1987) for the removal of the condition restricting the building over of the atrium void area other than by a glazed roof.
Submission of details of District Heating Network File Note pursuant to condition 10 of Planning Permission 25/00041/FULMAJ dated 19.02.2026.
Installation of secondary glazing.
Installation of secondary glazing.
Installation of artwork along the junction of the landscaped space and the walls of St Ethelburga's Centre of Reconciliation and Peace.
Submission of Lighting Strategy pursuant to discharge of condition 10 of planning permission 23/01384/FULL dated 30.09.2024.
Submission of Climate Change Resilience Sustainability Statement pursuant to discharge of condition 15 of planning permission 25/00041/FULMAJ dated 19.02.2026.
Refurbishment works to part of the mezzanine floor and associated staircase
External alterations to southern frontage and internal redecoration and refurbishment of ground floor and basement levels.
Installation of brass cill covers to 7no. ground floor windows.
Application for non-material amendments under s96a of the Town and Country Planning Act 1990 (as amended) to amend Condition 38 (Approved Drawings) pursuant to planning permission reference 25/00540/FULL (dated 7th November 2025) , namely for: internal layout reconfigurations; retention of existing lightwells on the Old Broad Street fa�ade; fa�ade alterations, including balustrading, louvres and glazing amendments; revisions to the approved planting and landscaping scheme; reconfiguration of the rooftop pergola; alterations to the rooftop plant enclosure; and associated design refinements
Submission of the Development Programme pursuant to Schedule 3 Paragraph 6.4 of the S106 Agreement dated 19th February 2026 (Planning Application Reference: 25/00041/FULMAJ).
Submission of details of Fire Safety Strategy Report (RIBA Stage 4) pursuant to condition 54 of Planning Permission 25/00041/FULMAJ dated 19.02.2026.
Submission of details of window finishes pursuant to condition 2(a) of Planning Permission 25/00540/FULL dated 07.11.2025.
Submission of details of Inclusive Fire Escape Strategy pursuant to condition 3(f) of Planning Permission 25/00540/FULL dated 07.11.2025.
Submission of Scheme of Protective Works - Construction pursuant to discharge of condition 7 of 25/00540/FULL dated 07.11.2025.
Submission of the Highways Schedule of Condition Survey pursuant to Schedule 3 Paragraphs 6.1-6.2 of the S106 Agreement dated 19th February 2026 (Planning Application Reference: 25/00041/FULMAJ).
Submission of details pursuant to the partial discharge of condition 7 of Planning Permission 23/01384/FULL dated 30.09.2024.
Installation of a) 2 x security cameras to north elevation; b) 6 x security cameras, anti-climb spikes, anti-climb barriers and security spikes above 4th floor level on east elevation; c) 2 x security cameras, anti-climb spikes, anti-climb barriers and security spikes at 4th floor level on south elevation; d) 3 x security cameras, anti-climb barriers and security spikes at 4th floor level on west elevation;
Submission of details of Site Condition Survey pursuant to condition 3 of Planning Permission 25/00041/FULMAJ dated 19.02.2026.
Submission of details of noise pursuant to the partial discharge of condition 6 of Planning Permission 23/01384/FULL dated 30.09.2024.
Installation of a canopy to the eastern elevation of the building.
Submission of details of pertaining to TFL infrastructure pursuant to conditions 41 and 42 of planning permission 25/00041/FULMAJ dated 19/02/2026.
Local Procurement Strategy ('LPS') S106 Agreement under Schedule 3, Para 2.1. of the S106 Agreement dated 19th February 2026 (Planning Application Reference: 25/00041/FULMAJ).
Submission of the Local Training Skills and Job Brokerage Strategy pursuant to Schedule 3 Paragraph 3.2-3.4 of the S106 Agreement dated 19th February 2026 (Planning Application Reference: 25/00041/FULMAJ).
Submission of the Local Procurement Strategy pursuant to Schedule 3 Paragraph 2.1 of the S106 Agreement dated 19th February 2026 (Planning Application Reference: 25/00041/FULMAJ).
Submission of details of Deconstruction Logistics Plan pursuant to condition 21 of Planning Permission 25/00041/FULMAJ dated 19.02.2026.
Submission of details of acoustic report pursuant to condition 2(b) of Planning permission 25/00369/FULL dated 09.05.2025.
Submission of details of Demolition - Noise, Dust and Vibration Management Plan and Demolition - Scheme of Protective Works pursuant to condition 19 of Planning Permission 25/00041/FULMAJ dated 19.02.2026.
Submission of details of signage for all aspects of the building pursuant to condition 18(c) of Planning permission 23/01384/FULL dated 30.09.2024.
Submission of details of rooftop including any plant equipment and the roofscape and screening to M and E pursuant to the partial discharge of condition 18 part (e) of Planning permission 23/01384/FULL dated 30.09.2024.
Submission of the Local Training, Skills, and Job Brokerage Strategy (Demolition and Construction) pursuant to Schedule 3, Paragraph 3.2 and 3.5 of the S106 Agreement dated 7th November 2025 (Planning Application Reference: 25/00540/FULL).
Submission of the Development Programme pursuant to Schedule 3, Paragraph 6.4 of the S106 Agreement dated 7th November 2025 (Planning Application Reference: 25/00540/FULL).
Submission of a Climate Change Resilience Sustainability Statement (CCRSS) pursuant to condition 21 of planning permission 25/00540/FULL dated 07/11/2025.
Submission of details of the emergency power supply pursuant to the partial discharge of condition 34 of planning permission 25/00540/FULL dated 07/11/2025.
Submission of the Highways Schedule of Condition Survey pursuant to Schedule 3 Paragraph 6.1 of the S106 Agreement dated 7th November 2025 (Planning Application Reference: 25/00540/FULL).
Submission of an updated Sustainability and Energy Assessment pursuant to Condition 24 of planning permission 25/00540/FULL dated 07/11/2025.
Submission of details of access to the roof for cleaning and maintenance, including details of mansafe equipment pursuant to condition 18 (part H) of planning permission 23/01384/FULL dated 30/09/2024.
Facade cleaning to Old Broad Street elevation of 13-17 Old Broad Street using facade gommage.
Submission of details pursuant to condition 6 (BMU Maintenance) of planning permission 23/00918/FULL dated 24/01/2024.