Skip to content

Oaklands Farm Solar Park, Coton Road, Walton upon Trent, DE12 8LP

DMOT/2026/1341Pending Decision
Discharge / amendments

Proposal

Approval of details required by requirement 17 - Surface and Foul Water Drainage - (in relation to Phases 5 and 6) of permission ref. 2025 No. 739 - The Oaklands Farm Solar Park Order 2025 relating to a generating station with a gross electrical output ca

Received
11 October 2026
Approximate location: the centre of the postcode, not the exact property.
  1. Received11 Oct
  2. Validated11 Oct
  3. Consult.
  4. Target
  5. Decided

This is a planning application for a solar installation at Oaklands Farm Solar Park, Coton Road, Walton upon Trent, DE12 8LP. South Derbyshire has handled 4,179 applications of this type and approves 91% of them, typically deciding them in 58 days. It was submitted on 11 October 2026 and is still awaiting a decision. There have been 15 other applications at this address. We hold 1,217 applications in total for the DE12 postcode area.

Application Details

Reference
DMOT/2026/1341
Address
Oaklands Farm Solar Park, Coton Road, Walton upon Trent, DE12 8LP
Postcode
DE12 8LP
Local Authority
South Derbyshire
Decision Status
Undecided
Current Status
Under Consultation

Applicant & Agent

Planning Application Dates

Date Validated
11 October 2026
Date Submitted
11 October 2026

Planning Decision

Publicity

Appeal

Additional Information

Coordinates
52.746246, -1.670006
Enriching application data
2/3
Council recordsAppealsFlood risk

Source: South Derbyshire

Track this application

Get email alerts when there is a planning decision or status change.

Get email alerts near DE12

New planning applications delivered to your inbox weekly.

Planning history at this site

12 other applications at this property, newest first.

  1. 2026
    29 Sep

    Approval of details required by requirement 11 (Operational Environmental Management Plan) in relation to…

    PendingDischarge of conditionsDMOT/2026/1324
  2. 2026
    29 Sep

    Approval of details required by requirement 9 (M) (Surface Water Management Plan for CEMP) in relation to…

    PendingDischarge of conditionsDMOT/2026/1323
  3. 2026
    15 Sep

    Approval of details required by Requirement 15 (Operational Noise) for Phases 5 (EBOP and Substation) and 6…

    PendingDischarge of conditionsDMOT/2026/1244
  4. 2026
    15 Sep

    Approval of details required by Requirement 5 - Detailed Design (Phase 5 (EBOP and Substation)) of permission…

    PendingDischarge of conditionsDMOT/2026/1243
  5. 2026
    28 Aug

    Approval of details required by requirements 8 (LEMP phase 5) of permission ref. Oaklands Farm Solar Park…

    PendingDischarge of conditionsDMOT/2026/1154
  6. 2026
    15 May

    Approval of details required by requirement 17 (Surface Water and Foul Water Drainage) in relation to phases…

    PendingDischarge of conditionsDMOT/2026/0657

What's been approved on your street?

See what the council approved and refused near this address for the project you have in mind, and the rules that apply here.

Get The Signal Report