Lands approximately 120M North of 184 Omagh Road Ballygawley Dungannon
Approved on 14 September 2026
Council decision: Permission GrantedDelegated (officer decision)7 conditions
Proposal
Proposed 110kV substation compound, single storey switch and control room building, amended landscaping and associated development works, to serve previously approved Battery Energy Storage System (BESS) development site (approval planning reference LA09/2023/1354/F). This proposed 110kV substation is proposed in lieu of previously approved substation compound, building and associated infrastructure. (There are no proposed amendments to the previously approved BESS units or MV-Skids).
- Received
- 11 November 2025
- Decision level
- Delegated (officer decision)
- Public comments
- 0 · last counted 7 November 2026
- Council
- Mid Ulster District Council
- Ward
- Augher And Clogher
- ReceivedReceived11 Nov
- ValidatedValidated11 Nov
- Consult.Consultation26 Feb
- TargetTarget Date24 Feb
- DecidedDecided14 Sep
Decided in 307 days (council typically 105)
About this application
This is a full planning application at Lands approximately 120M North of 184 Omagh Road Ballygawley Dungannon. Mid Ulster has handled 1,569 applications of this type. This one was decided in 307 days, 29 weeks longer than Mid Ulster's typical decision time. There are no previous applications recorded at this address. In the past year there have been 38 applications across Augher And Clogher.
100% of full applications at Mid Ulster District Council were approved. Across all application types, the council typically decides in about 15 weeks (median).
Based on decided applications received in the last 3 years.Planning something similar? See what gets approved on your street
Application details
- Application type
- Full
- Scale / size
- Medium
- Parish
- Clogher Valley
Planning application dates
- Date validated
- 11 November 2025
- Consultation expiry
- 26 February 2026
- Consultation end
- 26 February 2026
- Last date for comments
- 26 February 2026
- Target decision date
- 24 February 2026
Applicant and agent
- Applicant
- Private applicant
Planning decision
- Case officer
- Deirdre Laverty
- Statutory period
- 105 days
Publicity
- Last advertised
- 24 November 2025
Additional information
- Documents
- 56
Site constraints
Source: Mid Ulster
Track this application
Get email alerts when there is a planning decision or status change.
Around this site
Nearby applications
- Lands immediately South of Omagh Road and Approx. 150M Northeast of No 174 Omagh Road GarvaghyLA09/2026/0607/PANAwaiting decision0.4 mi
- Approx 115M S.E of 29 Rarogan Rd Garvaghy BallygawleyLA09/2026/0821/O · OutlineAwaiting decision1.2 mi
- Landa Approx 35M South of No 132 Omagh Road BallygawleyLA09/2025/1240/F · FullApproved1.2 mi
- Approx 250M South West of 24 Rarogan Road Garvaghy BallygawleyLA09/2026/0693/RM · OutlineApproved1.5 mi
For applicants and trades
Contractors near this project
- Thomas Allen Electrical ContractorElectrician1.6 mi
- Clogher Valley ElectricalElectrician3.9 mi
- Tyrone Fabrication LtdElectrician5.3 mi
- Dmc.Ni LimitedElectrician5.3 mi
Planning something similar?
See what the council approved and refused on your street for the project you have in mind. Pick your home and get the evidence before you pay for drawings.