DWNO Reinforcement Project - Uprating of XX and XR Overhead Lines from 275kV to 400kV and ancillary works
Proposal
The application proposes the uprating of existing overhead lines (OHL) XX and XR routes from 275kV to 400kV. XX OHL runs between Easterhouse substation and Newarthill substation. While XR route runs between Newarthill substation and Wishaw substation. The uprating shall comprise replacement of existing conductors (overhead line wires), downleads, temporary accesses, tower foundation upgrades and tower strengthening. Four new towers are proposed on XX route at Glenmavis where the proposed new OHL (WB route) connects to XX route. Two permanent towers and one temporary tower are proposed adjacent to Newarthill substation. Ancillary development includes the following: extension to Wishaw substation comprising an extension of the existing substation platform, gantries, outdoor air insulated switch gear, gas insulated busbars, drainage and associated security boundary fence.
- Received
- 12 June 2026
- Council
- Energy Consents Unit
- ReceivedReceived12 Jun
- ValidatedValidated
- Consult.Consultation
- TargetTarget Date
- DecidedDecided
Have your say
About this application
This is an outline application for an extension at DWNO Reinforcement Project - Uprating of XX and XR Overhead Lines from 275kV to 400kV and ancillary works. Energy Consents Unit has handled 139 applications of this type. It has been with the council since 12 June 2026 and is still awaiting a decision. There are no previous applications recorded at this address.
100% of outline applications at Energy Consents Unit were approved. Across all application types, the council typically decides in about 15 weeks (median).
Based on decided applications received in the last 3 years.Planning something similar? See what gets approved on your street
Application details
- Application type
- Development
- Development type
- Overhead Power Line (EIA)
- Scale / size
- Medium
- District
- North Lanarkshire Council
Planning application dates
- Validated
- 12 June 2026
Applicant and agent
- Applicant
- SP Transmission Plc
Additional information
- Documents
- 24
Site constraints
Source: Energy Consents Unit
Track this application
Get email alerts when there is a planning decision or status change.
Around this site
Nearby applications
- LT294/295 Bhlaraidh Extension Wind Farm Grid Connection WorksECU00006368 · OutlineAwaiting decision0.0 mi
- Hawick Substation to V Route 132kV Grid WorksECU00005220 · OutlineApproved0.0 mi
- DWNO Reinforcement Project - Uprating of ZG Overhead Line from 275kV to 400kV and ancillary worksECU00006375 · OutlineAwaiting decision0.0 mi
- 1 Astwood Villa Astwood Lane Stoke Prior Bromsgrove B60 4BBW/24/00754/HP · FullApproved0.3 mi
- 1 Astwood View Cottages Causeway Meadows Stoke Prior Hanbury Bromsgrove B60 4BQW/25/02125/CLPU · OutlineApproved0.3 mi
For applicants and trades
Contractors near this project
- M3 Global Flood Technologies LtdVerifiedWindow & Door InstallersProperty Flood Resilience3.4 mi
- LHM ElectricalElectrician0.3 mi
- UK Electrical Installations LtdElectricianCommercial & industrial electrical installations0.7 mi
- Arrow Services (Midlands) LtdElectrician0.8 mi
Planning something similar?
See what the council approved and refused on your street for the project you have in mind. Pick your home and get the evidence before you pay for drawings.