ECU00006262Planning Application ECU00006262
Outline application at 33kV EHV spur comprising single span to connect Limekiln Wind Farm substation, by Reay, Thurso, Caithness, Energy Consents Unit. View planning documents, track the decision and get email alerts on updates.
New 33kV EHV overhead line spur comprising a single span of 22 metre length supported by wooden poles of 10 metre height comprising one single wooden pole and one double (H) terminal pole located within the planning authority area of Highland Council by Limekiln Substation (Limekiln Wind Farm), Reay, Thurso, Caithness
ECU00006262
33kV EHV spur comprising single span to connect Limekiln Wind Farm substation, by Reay, Thurso, Caithness
This is an outline application at 33kV EHV spur comprising single span to connect Limekiln Wind Farm substation, by Reay, Thurso, Caithness. Energy Consents Unit has handled 107 applications of this type and approves nearly all of them, typically deciding them in 110 days. It was submitted on 24 October 2025 and is still awaiting a decision. There are no previous applications recorded at this address.
Track this application
Get email alerts when there is a planning decision or status change.
Application Details
Applicant & Agent
Planning Application Dates
Planning Decision
Publicity
Appeal
Additional Information
Source: Energy Consents Unit