Six Oaks Renewable Energy Park Newmarket Road Bottisham Cambridgeshire
Proposal
Non material amendment to pre-commencement conditions to previously approved 22/01291/ESF for installation of a Renewable Energy Park comprising: ground mounted solar panels; access tracks; inverters, transformers; substation and battery energy storage system; customer cabin; underground cables and conduits; perimeter fence; CCTV equipment; temporary construction compound; and associated infrastructure and planting scheme
- Received
- 15 April 2026
- ReceivedSubmitted15 Apr
- ValidatedValidated
- Consult.Consultation
- TargetTarget Date
- DecidedDecided
This is a planning application for a solar installation at Six Oaks Renewable Energy Park Newmarket Road Bottisham Cambridgeshire. East Cambridgeshire has handled 4,044 applications of this type and approves 93% of them, typically deciding them in 50 days. It was submitted on 15 April 2026 and is still awaiting a decision. There has been 1 other application at this address.
Application Details
Applicant & Agent
Planning Application Dates
Planning Decision
Publicity
Appeal
Additional Information
Source: East Cambridgeshire
Track this application
Get email alerts when there is a planning decision or status change.
Associated applications
- 202624 Jul
To discharge Conditions 3 (CTMP), 4 (Sufficient Vehicle Turning), 7 (Surface Water), 14 (CEMP) and 16(Soft…
PendingDischarge of conditions22/01291/DISA - 202615 Apr
Non material amendment to pre-commencement conditions to previously approved 22/01291/ESF
This applicationPendingNon-material amendment22/01291/NMAA