Skip to content

Land At Trevallyn Tremar Cornwall

E2/08/02180/OHLOverhead Electricity LinesApproved

Approved on 29 January 2009

Council decision: Approved (Statutory/one condition only)Delegated (officer decision)

Proposal

Erection of one wooden terminal pole and stay and one wooden lazy leg pole alongside to site the pole mounted transformer

Received
8 December 2008
Decision level
Delegated (officer decision)
Public comments
1
Ward
St Cleer And St Neot
  1. Received8 Dec
  2. Validated8 Dec
  3. Consult.31 Dec
  4. Target2 Feb
  5. Decided29 Jan

Decided in 52 days (council typically 49)

About this application

This is a planning application at Land At Trevallyn Tremar Cornwall. Cornwall has handled 234 applications of this type. This one was decided in 52 days, 3 days longer than Cornwall's typical decision time. The site is in 1 listed building nearby. There are no previous applications recorded at this address.

94% of all applications at Cornwall Council were approved. Across all application types, the council typically decides in about 7 weeks (median).

Based on decided applications received in the last 3 years.See what's approved near your address

Application details

Application type
Overhead Electricity Lines
Scale / size
Small
Parish
St. Cleer

Planning application dates

Date validated
8 December 2008
Consultation expiry
6 January 2009
Consultation start
10 December 2008
Consultation end
31 December 2008
Neighbour consultation start
10 December 2008
Neighbour consultation end
31 December 2008
Target decision date
2 February 2009
Decision issued
30 January 2009
Application expires
8 January 2009

Planning decision

Statutory period
56 days

Publicity

Site notice start
16 December 2008
Site notice end
6 January 2009

Additional information

Documents
5
Constraints
3

Site constraints

Checking the site
2/3
Council recordsAppealsFlood risk

Designations at the address point. Ones next to the site may also apply.

  • Flood zone 1: Low probability (rivers and sea)

Not published by this council, so not checked: Article 4 directions and tree preservation orders. Ask the council if these matter.

Also checked, none recorded (22)

flood storage areas, conservation areas, listed buildings, green belt, scheduled monuments, World Heritage Sites, World Heritage Site buffer zones, registered parks and gardens, registered battlefields, Heritage at Risk entries, nutrient neutrality catchments, national parks, National Landscapes, SSSIs, Special Areas of Conservation, Special Protection Areas, Ramsar sites, ancient woodland, national nature reserves, local nature reserves, heritage coasts and brownfield registers.

A guide only, from official open data; it is not a planning search. Flood zones cover rivers and sea, not surface water.

Data © Crown copyright and others · sources and licences

Contains public sector information from planning.data.gov.uk (MHCLG and local planning authorities), licensed under the Open Government Licence v3.0. © Crown copyright and database right 2026.

© Historic England 2026. Contains Ordnance Survey data © Crown copyright and database right 2026. The Historic England GIS Data contained in this material was obtained on 2026-11-03. The most publicly available up to date Historic England GIS Data can be obtained from HistoricEngland.org.uk.

© Natural England copyright. Contains Ordnance Survey data © Crown copyright and database right 2026.

© Environment Agency copyright and/or database right 2026. All rights reserved. Flood Map for Planning, Open Government Licence v3.0.

Contains Ordnance Survey data © Crown copyright and database right 2026.

Source: Office for National Statistics licensed under the Open Government Licence v.3.0. Contains OS data © Crown copyright and database right 2026.

Source: Cornwall

Track this application

Get email alerts when there is a planning decision or status change.

Around this site

For applicants and trades

What's been approved on your street?

See what the council approved and refused near this address for the project you have in mind, and the rules that apply here.

Get The Signal Report