Central Electricity Generating Station Mop End Lane Mop End Buckinghamshire
Approved on 16 December 2022
Council decision: Conditional permissionDelegated (officer decision)
Boundary © HM Land Registry, © Ordnance Survey · details
This information is subject to Crown copyright and database rights 2026 and is reproduced with the permission of HM Land Registry. The polygons (including the associated geometry, namely x, y co-ordinates) are subject to Crown copyright and database rights 2026 Ordnance Survey AC0000851063. Conditions of use.
Proposal
Extension to the existing Amersham National Grid substation, temporary laydown / welfare area and the upgrading of an access track around the north part of the substation.
- Received
- 17 June 2022
- Decision level
- Delegated (officer decision)
- Council
- Chiltern South Bucks
- Ward
- Penn Wood & Old Amersham
- ReceivedReceived17 Jun
- ValidatedValidated17 Jun
- Consult.Consultation13 Dec
- TargetTarget Date9 Dec
- DecidedDecided16 Dec
Decided in 182 days (council typically 56)
About this application
This is a full planning application for an extension at Central Electricity Generating Station Mop End Lane Mop End Buckinghamshire. Chiltern South Bucks has handled 8,004 applications of this type. This one was decided in 182 days, 18 weeks longer than Chiltern South Bucks's typical decision time. There have been 4 other applications at this address.
82% of full applications at Chiltern South Bucks were approved. Across all application types, the council typically decides in about 8 weeks (median).
Based on decided applications received in the last 3 years.Planning something similar? See what gets approved on your street
Application details
- Application type
- Full Application
- Scale / size
- Medium
- Parish
- Amersham
Planning application dates
- Date validated
- 17 June 2022
- Consultation expiry
- 13 December 2022
- Consultation start
- 5 December 2022
- Consultation end
- 13 December 2022
- Last date for comments
- 13 December 2022
- Target decision date
- 9 December 2022
Applicant and agent
- Agent
- National Grid
- Agent address
- National Grid House Warwick Technology Park Gallows Hill Warwick CV34 6DA
Planning decision
- Statutory period
- 175 days
Publicity
- Site notice start
- 21 July 2022
- Site notice end
- 11 August 2022
Additional information
- Documents
- 23
Site constraints
Designations that overlap or adjoin the site outline.
- Article 4 direction: Whole District excluding the Town of Chesham - Poultry production.
- Green belt: Buckinghamshire
- National Landscape (AONB): Chilterns
- Ancient woodlandPart of the site · +1 more
- Flood zone 1: Low probability (rivers and sea)
Also checked, none recorded (19)
flood storage areas, conservation areas, listed buildings, tree preservation orders, scheduled monuments, World Heritage Sites, World Heritage Site buffer zones, registered battlefields, Heritage at Risk entries, nutrient neutrality catchments, national parks, SSSIs, Special Areas of Conservation, Special Protection Areas, Ramsar sites, national nature reserves, local nature reserves, heritage coasts and brownfield registers.
A guide only, from official open data; it is not a planning search. Flood zones cover rivers and sea, not surface water.
Data © Crown copyright and others · sources and licences
Contains public sector information from planning.data.gov.uk (MHCLG and local planning authorities), licensed under the Open Government Licence v3.0. © Crown copyright and database right 2026.
© Historic England 2026. Contains Ordnance Survey data © Crown copyright and database right 2026. The Historic England GIS Data contained in this material was obtained on 2026-11-03. The most publicly available up to date Historic England GIS Data can be obtained from HistoricEngland.org.uk.
© Natural England copyright. Contains Ordnance Survey data © Crown copyright and database right 2026.
© Environment Agency copyright and/or database right 2026. All rights reserved. Flood Map for Planning, Open Government Licence v3.0.
Contains Ordnance Survey data © Crown copyright and database right 2026.
Source: Office for National Statistics licensed under the Open Government Licence v.3.0. Contains OS data © Crown copyright and database right 2026.
Associated applications
- 20233 Mar
Application for approval of details subject to condition 3 (Precautionary Method Statement) of planning…
Condition AcceptedDischarge of conditionsPL/23/0734/CONDA - 202217 Jun
Extension to the existing Amersham National Grid substation, temporary laydown / welfare area and the…
This applicationApprovedFullPL/22/2179/FA
Planning history at this site
1 other application at this property, newest first.
Source: Chiltern South Bucks
Track this application
Get email alerts when there is a planning decision or status change.
Around this site
Nearby applications
- National Grid Substation Mop End Lane AmershamPL/23/0734/CONDA · ConditionsApproved0.0 mi
- Amersham Field Centre Mop End Lane Mop End Buckinghamshire HP7 0QPPL/20/2351/FA · FullApproved0.0 mi
- Amersham Field Study Centre Mop End Lane Mop End BuckinghamshireCH/2003/0665/FA · FullApproved0.1 mi
- Central Electricity Generating Station Mop End Lane Mop End BuckinghamshirePL/26/01876/CONDA · ConditionsAwaiting decision0.1 mi
- Central Electricity Generating Station Mop End Lane Mop End BuckinghamshirePL/23/2097/FA · FullAwaiting decision0.1 mi
For applicants and trades
Contractors near this project
- Lynford homesVerifiedBuckinghamshireNew Builds6.7 mi
- Acentia Solar LtdElectrician0.9 mi
- Acentia Electrical LtdElectrician0.9 mi
- W12 Electrical LtdElectrician1.2 mi
Planning something similar?
See what the council approved and refused on your street for the project you have in mind. Pick your home and get the evidence before you pay for drawings.