Land East Of Osborne Lane Warfield Bracknell Berkshire

25/00796/FULFull planning permissionRefused
Full

Refused on 28 August 2026

Council decision: RefuseDelegated (officer decision)11 reasons for refusal

Approximate site (title boundary)
Boundary © HM Land Registry, © Ordnance Survey · details

This information is subject to Crown copyright and database rights 2026 and is reproduced with the permission of HM Land Registry. The polygons (including the associated geometry, namely x, y co-ordinates) are subject to Crown copyright and database rights 2026 Ordnance Survey AC0000851063. Conditions of use.

Proposal

Erection of 32 dwellings, with associated access, drainage works, tree works, woodland management, open space and landscaping.

Received
19 December 2025
Decision level
Delegated (officer decision)
Ward
Binfield North & Warfield West
  1. Received19 Dec
  2. Validated19 Dec
  3. Consult.28 Aug
  4. Target28 Aug
  5. Decided28 Aug

Decided in 252 days (council typically 56)

About this application

This is a full planning application for a new dwelling at Land East Of Osborne Lane Warfield Bracknell Berkshire. Bracknell has handled 504 applications of this type. This one was decided in 252 days, 28 weeks longer than Bracknell's typical decision time. The site is in the Teignmouth Town Centre conservation area, with 12 listed buildings nearby. There are no previous applications recorded at this address. In the past year there have been 70 applications across Binfield North & Warfield West.

91% of full applications at Bracknell Forest Council were approved. Across all application types, the council typically decides in about 8 weeks (median).

Based on decided applications received in the last 3 years.Planning something similar? See what gets approved on your street

Why it was refused

  1. The proposed development is located outside the defined settlement boundary, within an area of countryside. The proposal would result in an unacceptable and urbanising encroachment of built development into the countryside, on a site which does not relate well to the existing settlement. The proposal is therefore contrary to policies LP 1, LP 2 and LP 35 of the Bracknell Forest Local Plan (2024), Policy WNP7 of the Warfield Neighborhood Plan and policies DP3 and S5 of the National Planning Policy Framework (2026).
  2. The proposed works would cause harm to the significance of a number of designated heritage assets by virtue of unsympathetic development within their setting. As such the development fails to comply with the statutory duty set out in s66(1) of the Planning (Listed Building and Conservation Area) Act 1990 (as amended), policy LP29 of the Local Plan and policy HE 6 of the NPPF (2026).
  3. The proposed development of this site would lead to the unacceptable loss of ‘very high distinctiveness’, irreplaceable priority habitat of county- level importance, contrary to BFLP Policy LP 53, NPPF Policy N6, the Biodiversity Gain Hierarchy set out in Articles 37A and 37D of the Town and Country Planning (Development Management Procedure) (England) Order 2015 and the Biodiversity and Green Infrastructure SPD.
  4. The development would have an adverse urbanising impact upon the character and appearance of the site and surrounding landscape, would fail to protect, enhance and respond positively to the defined characteristics and valued features of the relevant Landscape Character Area. The proposal is therefore contrary to policies LP 35, LP 36, LP 53 and LP 54 of the Bracknell Forest Local Plan (2024), policies WNP7 and WNP8 of the Warfield Neighborhood Plan and policies DP3, S5, N2 and N6 of the National Planning Policy Framework.
  5. The application fails to demonstrate that the proposal and any required highway works would not result in the loss of trees, including protected trees, considered important to the character and appearance of the area. The proposal is therefore contrary to policies LP30, LP35, LP36 and LP54 of the Bracknell Forest Local Plan (2024), Policy WNP8 of the Warfield Neighborhood Plan and policies DP3, S5, N2 and N6 of the National Planning Policy Framework.
  6. The application does not demonstrate that it protects and enhances biodiversity in accordance with policy LP53, NPPF Policy N2, Circular 06/05 and Conservation of Habitats and Species Regulations 2017 and the Biodiversity and Green Infrastructure SPD.
  7. The application fails to demonstrate that the development site can be appropriately drained. As such the scheme would be contrary to BFLP Policy LP 57 and Policy F8 of the NPPF (2026).
  8. It has not been demonstrated that the proposed development can be safely accessed, and that appropriate levels of parking will be provided on site. As such the development is considered contrary to BFLP policies LP 25, LP 60, LP 62 and policies TR4 and TR6 of the NPPF (2026).
  9. In the absence of a legal agreement, it has not been demonstrated that the development will provide suitable on-site affordable housing contrary to BFLP Policy LP16 and the NPPF Policy H08.
  10. In the absence of a planning obligation to secure suitable avoidance and mitigation measures and access management monitoring arrangements, in terms that are satisfactory to the Local Planning Authority, the proposal would be contrary to Regulation 63(5) of the Conservation of Habitats and Species Regulations 2017 (as amended), Policy NRM6 of the South East Plan, Policy LP31 and 32 of the Bracknell Forest Local Plan, the Thames Basin Heaths Special Protection Area Supplementary Planning Document (2025), and Policy N6 of the NPPF (2026).
  11. In the absence of a completed legal agreement under section 106 of the Town and Country Planning Act 1990, the proposal fails to secure the planning obligations necessary to make the development acceptable in planning terms. The development has not secured: the required financial contribution towards community facilities; the required active open space contribution and obligations relating to the provision, management and long-term maintenance of on-site active and passive open space; the delivery and long-term maintenance/monitoring of mandatory Biodiversity Net Gain; the required affordable housing provision; and any necessary monitoring arrangements. As such, the proposal would fail to mitigate its impacts on local infrastructure, community facilities, open space, green infrastructure, biodiversity and affordable housing need. The proposal is therefore contrary to Bracknell Forest Local Plan (2024) Policies LP 16, LP 24, LP 30, LP 44, LP 45, LP 46 and LP 53, the Bracknell Forest Planning Obligations SPD, the Warfield SPD, the Housing SPD, and the National Planning Policy Framework.

From the council's decision notice.

Application details

Application type
Full planning permission
Scale / size
Large
Number of dwellings
32
Parish
Warfield Parish Council

Planning application dates

Date validated
19 December 2025
Consultation expiry
28 August 2026
Consultation start
22 January 2026
Consultation end
28 August 2026
Neighbour consultation start
12 January 2026
Neighbour consultation end
2 February 2026
Last date for comments
4 February 2026
Target decision date
28 August 2026
Application expires
30 June 2026

Applicant and agent

Agent address
Woolf Bond Planning The Mitfords Basingstoke Road Three Mile Cross Reading Berkshire RG7 1AT

Planning decision

Statutory period
252 days

Appeal history

3373914
Dismissed
Type: Householder (HAS)Procedure: Written RepresentationsDecision: 2 December 2025Dev Type: Householder developmentsReason: Refusal

Additional information

Planning Portal ID
PP-14504927
Comments
0
Documents
125

Site constraints

Checking the site
2/3
Council recordsAppealsFlood risk

Designations that overlap or adjoin the site outline.

Not published by this council, so not checked: Article 4 directions and tree preservation orders. Ask the council if these matter.

Also checked, none recorded (21)

flood storage areas, conservation areas, green belt, scheduled monuments, World Heritage Sites, World Heritage Site buffer zones, registered parks and gardens, registered battlefields, Heritage at Risk entries, nutrient neutrality catchments, national parks, National Landscapes, SSSIs, Special Areas of Conservation, Special Protection Areas, Ramsar sites, ancient woodland, national nature reserves, local nature reserves, heritage coasts and brownfield registers.

A guide only, from official open data; it is not a planning search. Flood zones cover rivers and sea, not surface water.

Data © Crown copyright and others · sources and licences

Contains public sector information from planning.data.gov.uk (MHCLG and local planning authorities), licensed under the Open Government Licence v3.0. © Crown copyright and database right 2026.

© Historic England 2026. Contains Ordnance Survey data © Crown copyright and database right 2026. The Historic England GIS Data contained in this material was obtained on 2026-11-03. The most publicly available up to date Historic England GIS Data can be obtained from HistoricEngland.org.uk.

© Natural England copyright. Contains Ordnance Survey data © Crown copyright and database right 2026.

© Environment Agency copyright and/or database right 2026. All rights reserved. Flood Map for Planning, Open Government Licence v3.0.

Contains Ordnance Survey data © Crown copyright and database right 2026.

Source: Office for National Statistics licensed under the Open Government Licence v.3.0. Contains OS data © Crown copyright and database right 2026.

Source: Bracknell

Track this application

Get email alerts when there is a planning decision or status change.

Around this site

For applicants and trades

Planning something similar?

See what the council approved and refused for new homes on your street. Pick your home and get the evidence before you pay for drawings.