Land Between Bicker Drove And Bicker Fen Substation
Approved on 21 August 2026
5 conditions
Proposal
Proposed development of an electrical connection between previously approved connection on Bicker Drove and Bicker Fen Substation
- Received
- 23 April 2026
- Council
- Boston Borough Council
- ReceivedReceived23 Apr
- ValidatedValidated30 Apr
- Consult.Consultation13 Jul
- TargetTarget Date21 Aug
- DecidedDecided21 Aug
Decided in 113 days
About this application
This is a planning application at Land Between Bicker Drove And Bicker Fen Substation. Boston has handled 1,308 applications of this type. This one was decided in 113 days, 8 weeks longer than Boston's typical decision time. There has been 1 other application at this address.
Application details
Planning application dates
- Date validated
- 30 April 2026
- Consultation end
- 13 July 2026
- Target decision date
- 21 August 2026
Additional information
- Documents
- 16
Associated applications
- 202618 Sep
Application to discharge condition C3 (Root Protection) of Planning permission B/26/0190
RespondedDischarge of conditions01563/26/DPC - 202630 Apr
Proposed development of an electrical connection between previously approved connection on Bicker Drove and…
This applicationApprovedApplicationB/26/0190
Source: Boston
Track this application
Get email alerts when there is a planning decision or status change.
Around this site
For applicants and trades
What's been approved on your street?
See what the council approved and refused near this address for the project you have in mind, and the rules that apply here.
Get The Signal Report