Operate and keep installed approximately 105.2 kilometre (km) 400 kV Overhead Line (OHL), supported on steel lattice tower structures including downleads, between a proposed new substation named Emmock near to Tealing in Angus and an existing substation at Kintore, Aberdeenshire

25/00512/S37

Large
Other

New Substation At Emmock Near Tealing And An Existing Substation At Kintore Aberdeenshire

Submitted19 Sept
Validated
Consultation
Target
Decided19 Nov
9 weeks typical decision time in Angus100% of other applications approved

This is a planning application at New Substation At Emmock Near Tealing And An Existing Substation At Kintore Aberdeenshire. Angus has handled 8 applications of this type and approves nearly all of them, typically deciding them in 286 days. This one was decided in 61 days, 32 weeks quicker than Angus's median. There are no previous applications recorded at this address. In the past year there have been 34 applications across Monifieth & Sidlaw.

Track this application

Get email alerts when there is a planning decision or status change.

Application Details

Reference
25/00512/S37
Address
New Substation At Emmock Near Tealing And An Existing Substation At Kintore Aberdeenshire
Local Authority
Angus
Application Type
Other
Scale / Size
Large
Decision Status
Permitted

Applicant & Agent

Planning Application Dates

Date Decided
19 November 2025
Date Submitted
19 September 2025

Planning Decision

Publicity

Appeal

Additional Information

Coordinates
56.671734, -2.925072