Electricity Sub Station Forfar

25/00120/EIASCREIA ScreeningApproved
Outline / PiP

Approved on 6 March 2025

Council decision: EIA NOT RequiredDelegated (officer decision)

Proposal

Lunanhead 132/33 kV Grid Supply Point (GSP) Substation Upgrade

Received
4 February 2025
Decision level
Delegated (officer decision)
Ward
Forfar & District
  1. Received4 Feb
  2. Validated5 Mar
  3. Consult.
  4. Target26 Mar
  5. Decided6 Mar

Decided in 1 day (council typically 56)

About this application

This is an outline application at Electricity Sub Station Forfar. Angus has handled 305 applications of this type. This one was decided in 30 days, 4 weeks quicker than Angus's typical decision time. There are no previous applications recorded at this address. In the past year there have been 18 applications across Forfar & District.

96% of outline applications at Angus Council were approved. Across all application types, the council typically decides in about 8 weeks (median).

Based on decided applications received in the last 3 years.See what's approved near your address

Application details

Application type
EIA Screening
Scale / size
Medium
Parish
Royal Burgh Of Forfar

Planning application dates

Date validated
5 March 2025
Target decision date
26 March 2025

Planning decision

Statutory period
21 days

Additional information

Comments
0
Documents
4

Site constraints

Checking the site
2/3
Council recordsAppealsFlood risk

Source: Angus

Track this application

Get email alerts when there is a planning decision or status change.

Around this site

For applicants and trades

What's been approved on your street?

See what the council approved and refused near this address for the project you have in mind, and the rules that apply here.

Get The Signal Report