Skip to content

Craignathro Wind Turbine Forfar

24/00480/EIASCREIA ScreeningApproved
Outline / PiP

Approved on 20 August 2024

Council decision: EIA NOT RequiredDelegated (officer decision)

Proposal

Screening opinion request for the repowering of an existing wind turbine (replacement of existing 33m high turbine with turbine with a tip height of 67m (54m rotor diameter, 40m hub height)

Received
2 August 2024
Decision level
Delegated (officer decision)
Ward
Forfar & District
  1. Received2 Aug
  2. Validated2 Aug
  3. Consult.
  4. Target23 Aug
  5. Decided20 Aug

Decided in 18 days (council typically 56)

About this application

This is an outline application at Craignathro Wind Turbine Forfar. Angus has handled 305 applications of this type. This one was decided in 18 days, 5 weeks quicker than Angus's typical decision time. There are no previous applications recorded at this address. In the past year there have been 18 applications across Forfar & District.

96% of outline applications at Angus Council were approved. Across all application types, the council typically decides in about 8 weeks (median).

Based on decided applications received in the last 3 years.See what's approved near your address

Application details

Application type
EIA Screening
Scale / size
Medium
Parish
Royal Burgh Of Forfar

Planning application dates

Date validated
2 August 2024
Target decision date
23 August 2024

Planning decision

Statutory period
21 days

Additional information

Comments
0
Documents
17

Site constraints

Checking the site
2/3
Council recordsAppealsFlood risk

Source: Angus

Track this application

Get email alerts when there is a planning decision or status change.

Around this site

For applicants and trades

What's been approved on your street?

See what the council approved and refused near this address for the project you have in mind, and the rules that apply here.

Get The Signal Report