Peterhead, Persley And Kintore
Proposal
Reconductoring of approximately 51 kilometres (km) of an existing 275 kilovolt (kV) overhead line (OHL), connecting substations between Peterhead and Kintore to enable operation at 400 kV, and approximately 12 km of existing 132 kV OHL connecting the existing Persley Tee to Persley Substation to enable operation at 275 kV
- Received
- 29 April 2026
- Target decision date
- 28 June 2026
- Council
- Aberdeen City Council
- ReceivedSubmitted29 Apr
- ValidatedValidated29 Apr
- Consult.Consultation
- TargetTarget Date28 Jun
- DecidedDecided
This is an outline application at Peterhead, Persley And Kintore. Aberdeen has handled 185 applications of this type and approves nearly all of them, typically deciding them in 29 days. It was submitted on 29 April 2026 and is still awaiting a decision. There are no previous applications recorded at this address.
Application Details
Applicant & Agent
Planning Application Dates
Planning Decision
Publicity
Appeal
Additional Information
Source: Aberdeen
Track this application
Get email alerts when there is a planning decision or status change.
What's been approved on your street?
See what the council approved and refused near this address for the project you have in mind, and the rules that apply here.