Planning Application Details - 25/03311/S37
Spittal to Beauly 400 kV OHL - Install, operate and keep installed 173km of new 400 kV overhead electricity line, supported on steel lattice tower structures, between proposed new substations at Banniskirk (ND 15905 56823) in the area of Spittal, and Fanellan (NH 48534 43208) in the area of Beauly, with a connection via a proposed new substation at Carnaig (NH 65053 97458) near to the existing substation at Loch Buidhe, in the area of Bonar Bridge; associated permanent diversion works to 18km of existing 132 kV and 275 kV overhead electricity lines, including the temporary diversion works, and ancillary development and associated works. This case will be determined by the Energy Consents Unit. Please visit Energy Consents Unit at https://www.energyconsents.scot/ApplicationSearch.aspx?T=2 using reference number ECU00006008
Application Details
- Reference
- 25/03311/S37
- Address
- Land 2430M SW Of Loch Buidhe Bonar Bridge
- Local Authority
- Highland
- Scale / Size
- Large
- Status
- Rejected
- Parish
- Creich Community Council
Applicant & Agent
Applicant Address: Per: Tara Cowley 10 Henderson Road Inverness IV1 1SN
Key Dates
- Date Received
- 2025-09-03
- Date Validated
- 2025-09-03
- Date Submitted
- 2025-09-03
- Consultation Expiry
- 2025-10-05
- Target Decision Date
- 2025-11-07
- Date Decided
- 2025-10-30
Decision
- Decision
- S37 Raise Objection
- Decided By
- Committee Decision
- Case Officer
- See source
Additional Information
- Coordinates
- 57.95693, -4.034698