Planning Application Details - CB/25/02017/FULL
Construction of a temporary Solar Farm, to include the installation of Solar Panels with transformers, a substation, a DNO control room, a customer substation, GRP comms cabin, security fencing, landscaping and other associated infrastructure and works.
Application Details
- Reference
- CB/25/02017/FULL
- Address
- Land south of Greenfield Road and Clayhill Farm, Greenfield Road, Westoning
- Local Authority
- Central Bedfordshire
- Application Type
- Full
- Scale / Size
- Large
- Status
- Rejected
- Parish
- Westoning
Applicant & Agent
Agent Address: Part 4th Floor Whitehall Quay II Leeds LS1 4HR
Key Dates
- Date Received
- 2025-06-20
- Date Validated
- 2025-06-23
- Date Submitted
- 2025-06-20
- Consultation Expiry
- 2025-12-31
- Target Decision Date
- 2025-09-22
- Date Decided
- 2026-02-20
Decision
- Decision
- Full Application - Refused
- Decided By
- Officer Delegated
- Case Officer
- See source
Additional Information
- Coordinates
- 51.982235, -0.4977712
Planning Constraints Identified
This application matches the following planning constraint categories:
- Flood & Drainage